RENEWABLE ENERGY


PROJECTS:

A. Projects Completed under CAPEX Model:

S. No.

Solar Projects

Capacity

Location

Status

Generation (in MWh)

Reduce CO2 Emission

1

Installation of Grid connected Roof Top Solar PV Plant on Roof Top CM Residence.

12 KWp

CM Residence

12 KWp Solar PV plant commissioned on 09.06.2015 and Generation started w.e.f. 03.07.2015 after Net meter provided by DISCOM.

23.05 MWh

12.22 Ton

2

Installation of Grid connected Roof Top Solar PV Plant on Roof Top Dy. CM Residence.

6 KWp

Dy. CM Residence

6 KWp Solar PV plant commissioned on 09.06.2015 and Generation started w.e.f. 18.08.2015 after Net meter provided by DISCOM.

7.11 MWh

3.78 Ton

3

Installation of Grid connected Roof Top Solar PV Plant on Roof Tops of GTPS/PPS#1 stations of IPGCL- PPCL.

362.5 KWp

GTPS ROOF: 100 KWp

PPCL#I ROOF: 262.5 KWp

Project Commissioned: 13.06.2016

Project Commissioned: 08.07.2016

91.36 MWh




200.34 MWh

45.44 Ton




106.18 Ton


Total Capacity

380.5 KWp



321.86 MWp

170.59 Ton


B. Projects Completed under RESCO Model:

S. No.

Solar Projects

Project Model

Aggregate Capacity

Location

Status

1

Installation of 2 MW grid connected roof top solar PV system in selected locations in Delhi - PHASE-I

RESCO

2 MWp


Group I - 1MWp

Group II
1 MWp

Project awarded:

Group-I:
M/s Hero Solar Energy Pvt.

Group-II: M/s Azure Power India Pvt. Limited

Solar PV projects commissioned : Phase-I 02 MW RESCO model:

S. No.

Solar Projects

Capacity

Status Report

Generation (in MWh)

1

Delhi Technological University

430 KWp

Solar PV Project Completed on 29.07.2016

326.144 MWh

2

Netaji Subhash Institute of Technology

326 KWp

Solar PV Project Completed on 12.08.2016.

208.144 MWh

3

Indira Gandhi Delhi Technical University for Women

168 KWp

Solar PV Project Completed on 28.08.2016.

90.722 MWh

4

Shaheed Sukhdev College of Business Studies

76 KWp

Solar PV Project Completed on 30.09.2016.

14.110 MWh

5

G.B. Pant Institute of Technology

197.16 KWp

Solar PV Project Completed on 23.07.2016.

151.400 MWh

6

DTC Depot Rohini-2

27.9 KWp

Solar PV Project Completed on 23.07.2016.

20.658 MWh

7

DTC Depot Rohini-4

44.64 KWp

Solar PV Project Completed on 23.07.2016.

33.841 MWh

8

DTC Depot Bawana

27.9 KWp

Solar PV Project Completed on 26.07.2016.

17.107 MWh

9

DTC Depot Kanjhawala

75.02 KWp

Solar PV Project Completed on 26.07.2016.

53.444 MWh

10

DTC Depot GTK

22.32 KWp

Solar PV Project Completed on 26.07.2016.

14.894 MWh

11

DTC Depot Peeragarhi

55.8 KWp

Solar PV Project Completed on 26.07.2016.

39.443 MWh

12

Zakir Hussain College

50.22 KWp

Solar PV Project Completed on 30.09.2016.

25.236 MWh

13

Janki Devi Memorial College

58.9 KWp

Solar PV Project Completed on 30.09.2016.

25.567 MWh

14

Vivekanand College

55.8 KWp

Solar PV Project Completed on 30.09.2016.

13.644 MWh

15

Hans Raj College

44.64 KWp

Solar PV Project Completed on 30.09.2016.

25.008 MWh

16

Shyam Lal College

85.25 KWp

Solar PV Project Completed on 30.09.2016.

33.988 MWh

17

District Court, Dwarka

197.6 KWp

Solar PV Project Completed on 14.02.2017.

34.668 MWh


Total

1918.5 KWp


1022.766 MWh


C. New Solar Projects:


S. No.

Solar Projects

Project Model

Aggregate Capacity

Location

Status

1

Installation of 5 MW grid connected roof top solar PV system in selected locations in Delhi - PHASE-II.

RESCO

05 MWp

Group I -
&
Group II - 2.5 MWp

Tender awarded to following vendors for 2.5 MW each Solar PV project @ 7.1 Crore per MW and levellized tariff of Rs. 5.10/ Unit

1. M/s Clean Max Energy
1. M/s Hero Solar Energy

PPA signed for 1780 Kwp with:

1. Delhi Tourism - Dilli Haat, Pitampura
2. Ambedkar Institute of Technology
3. Deen Dayal Upadhyaya College
4. Delhi Tourism - Dilli Haat, Janakpuri
5. Deshbandhu College
6. Integrated Institute of Technology
7. Aryabhat Institute of Technology
8. ITI, Jaffarpur
9. ITI, Mangolpuri
10. Veer Savarkar Basic Training Centre
11. Pusa Institute of Technology
12. Industrial Training Institute, Pusa
13. ITI, Dheerpur

2

Implementation of Grid connected roof top Solar PV system on CAPEX model in selected GNCTD schools in Delhi.

CAPEX model

650 KWp

22 Nos. of GNCTD School Buildings.

Work order dt.17.03.2017 issued to M/s Ujaas Energy Limited for 669 KWp capacity.

Site feasibility for 24 Nos. of sites is under progress.

3

Empanelment of applicants for implementation of grid connected roof top solar PV system of 76 MWp capacity under CAPEX model & RESCO Model on roof tops in Delhi State.

  05 Parts:

For Part A, B & C: CAPEX

For PART D & E: RESCO

76 MWp


54 MWp CAPEX


22 MWp RESCO

Private / society owned/ leased residential buildings & institutions in Delhi.

Technical Bids for Part A, part B, Part C, Part D & Part E opened on 16.02.2017.

Part A (CAPEX) for 1 KW to 5 KW: Price bids opened on 16.03.2017, with project cost:
L-1: Rs. 51,250/ KWp from DPG Sansthan for 1800 kWp.
L-2: Rs. 52,000/- from Add Watt Power.
L-3: Rs. 66,430/- from Sirius Electric.

Issue of letter of allocation is under progress.

Part B (CAPEX) for above 5 KW to 10 KW: Price bids opened on 16.03.2017, with project cost:
L-1: Rs. 61,890/ KWp from Surya International.
L-2: Rs. 62,000/- from Ujjwal Solar & Sunbeam Energy.
L-3: Project cost is Rs. 62,500/- from Sirius Electric.

Issue of letter of allocation is under progress.

Part C- (CAPEX) 22 Nos. Of Price bid opened on 07.04.2017 for above 10 KW to 500 KW, following project cost:
L-1: Rs.55,000/ KWp from Gensol Consultants Pvt. Ltd.
L-2: Rs.57,490/ KWp from DRS Energy Pvt. Ltd.
L-3: Rs.58,000/ KWp from MIDS.

Issue of letter of allocation is under progress.

Part D- (RESCO) Empanelment of vendor is completed and only one vendor i.e. M/s Bharti Waters Pvt. Ltd. is empanelled for 2.2 MWp. Tariff awarded is Rs. 3.34/unit inclusive of taxes (Escalation 5% per annum for 25 years). Levellized tariff is Rs. 4.96/ unit.

Part E-(RESCO): Empanelment of vendors is completed and 02 Vendors are empanelled at tariff @4.66/ Unit inclusive of taxes for 25 years, are as under:
1. M/s Bharti Waters Pvt. Ltd. for 2.2 MWp.
2. M/s Green Ripples Pvt. Ltd. for 02 MWp.

Status updated on 31 Mar, 2017.


 
 